Foundation excavation in Cyprus: volume, machine, days and cost

For a typical house on the island the foundation dig is one to three days of an excavator with its operator, plus the trucks that take the spoil away. Rock stretches it: where the bucket hits limestone a breaker goes on and the days roughly double. Operators price the digger per day or per job, and some give a per-m³ figure once they have seen the plot.

Updated 23 October 2026

Strip, pad or raft: what the drawing shows

The civil engineer chooses the foundation, from the ground and the weight of the building, and it is on the permit drawings. For the dig, only its shape matters. Strip footings are trenches along the walls, filled with reinforced concrete. Pad footings are square holes under the columns, usually joined by trenches for the tie beams; many houses on the island are a concrete frame and have these. A raft is one concrete slab under the whole building: the dig is a shallow, level box the size of the footprint plus a margin.

Trenches and pads are precise work to a line and a level with a narrow bucket; a raft is bulk digging with a wide one. A raft moves more soil but often takes no longer.

Working out the volume

The example is a house of 12 × 10 m on strip footings with one internal wall across the 10 m side, trenches 0.6 m wide and 1 m deep, and the same house on a raft dug 0.5 m deep. For your own house, use the figures on the drawing.

Length or area

Strip footings: Outer walls 2 × (12 + 10) = 44 m, plus the internal wall 10 m: 54 m of trench

Raft: Footprint plus 0.5 m all round: 13 × 11 = 143 m²

In the ground

Strip footings: 54 × 0.6 × 1 = about 32 m³

Raft: 143 × 0.5 = about 72 m³

Loose, on the truck (+25–30 %)

Strip footings: about 40–42 m³

Raft: about 89–93 m³

Tipper loads of 10–12 m³

Strip footings: 4–5 loads

Raft: 8–10 loads

As in the pool guide: rock and soil take up 25–30 % more room once dug, and a three-axle tipper carries 10–12 m³. On a sloping plot, add the cut that levels the platform; it can be bigger than the footings.

Which machine for which plot

Open land, a truck drives in

Machine: Excavator 8–14 t with its operator (5–8 t for a small house)

Why: Digs to line and level fast, loads the tippers directly

A big footprint, a raft or a basement, rock

Machine: Excavator 14–20 t with a breaker

Why: Carries the heavier breaker that gets through limestone

A tight town plot between walls, access under 3 m

Machine: Mini digger 3–5 t with its operator

Why: Passes a 1.5–3 m way in, works close to walls

Spoil has to cross the plot

Machine: Bobcat

Why: Carries spoil to the truck or a heap, then levels

The base before the concrete

Machine: Rammer in trenches; plate or small roller under a raft

Why: Compacts the bottom and the gravel layer

How many days

Strip or pad footings, about 30–40 m³

Soil: One day, 5–8 t

Rock: Two to three days, 8–14 t with a breaker

Raft, about 70 m³

Soil: One day, 8–14 t, with a Bobcat helping

Rock: One and a half to two days, 14 t with a breaker

The same footings on a tight plot, 3–5 t mini digger

Soil: One to two days

Rock: Three to five days with the breaker

If one tipper shuttles to a tip half an hour away, the digger stands and waits. Two tippers on rotation, or a heap that a Bobcat loads later, keep it digging.

What comes on top of the digger

  • Taking the spoil away. Priced per tipper load, tip fee inside. Clean soil and rock can often go to a nearby plot that needs fill, which is cheaper.
  • Breaking rock. The breaker adds to the rate (on a mini digger, €30–60 a day). You find out you need it when the bucket stops, so ask for the price with and without it.
  • The low-loader for a tracked excavator, priced by distance.
  • A street permit, only if the machine or trucks stand on a public road.

Per cubic metre, per day or per job

Operators on the island price an excavator with its operator by the hour with a minimum, or by the day. For a whole foundation some quote the job, and some quote per m³ after walking the plot. That figure does not carry from one plot to the next: behind it are how fast the ground digs (clay and sand quickly, limestone only with the breaker) and how far and how often the trucks go. A rate from a job on the Nicosia plain says little about a hillside plot above Limassol. Ask for the price per day and the number of loads, and any two quotes compare.

Mini diggerfrom €150 a day
Self-drive, 1–2 t
€150–220 a day, cheaper per day for a week
Self-drive, 3–5 t
€220–300 a day
With operator
€350–450 a day, or €50–70 an hour with a €150 minimum
Breaker or auger
€30–60 a day on top
Excavatorfrom €55 an hour
5–20 t with operator
€55–85 an hour, minimum 4–8 hours; about €450–700 a day
Low-loader transport of a tracked machine
separate, by distance
Taking the soil away
per tipper load, on top

What operators on the island usually quote (open listings and price lists, October 2026), VAT not included unless stated. Your operator confirms the exact price for your job before anything is agreed.

Book the dig

How it works

1

Describe the job

The machine, the height or the load, the address, the day. Photos of the site help the operator bring the right thing.

2

A local operator takes it

We pass the request to an operator who works in your area. Your request page shows when they accept and at what price.

3

The machine arrives

The operator brings it on the day you set, and takes it away when you are done. You pay them directly.

Questions about digging foundations

What people ask before their first booking.

How much does foundation digging cost in Cyprus?

An excavator with its operator is about €55–85 an hour with a minimum, or €450–700 a day. On top come the tipper loads, the breaker if there is rock, and the low-loader. A small house on soil is often one day and four or five loads.

Can I hire a digger without a driver for the foundations?

Excavators from 5 t up come with their operator on the island. A mini digger can be self-drive, but footings must follow a line and a level the engineer checks, so most people take the operator.

Who marks out the trenches?

The surveyor, the engineer or the builder sets out pegs and strings from the drawings before the dig. The operator digs to those lines; say in the request who will be on site.

Do I need a permit to dig foundations?

The foundations are covered by the building permit your architect or engineer applies for. On your plot the machine needs no separate permit; on a public road it does.

What if the digger hits rock halfway down?

The operator fits a breaker and the job takes longer. Give the address: on the hills above Limassol, in most of Paphos and around Nicosia, rock is common.